Nolensville New Construction: What Sewer Capacity Means for Buyers

"The applicant has been informed that they are moving forward at their own risk while sewer availability is still not being issued."

That sentence appears in a July 14, 2026 Nolensville Planning Commission staff report about a proposed 51-lot neighborhood on Kidd Road. Nearly the same wording shows up in the Van Slyke Farm annexation report sent to the Board of Commissioners on July 6, 2026. It appears again in an August 11, 2026 report on a 21-townhome proposal called Greenbrook East. Three projects, three reports, one repeated sentence.

For someone comparing new construction in Nolensville with Franklin, Spring Hill or Thompson's Station, that repeated line explains the market. The new homes you can tour in Nolensville this fall come from subdivisions that were approved before Metro Nashville stopped issuing sewer availability. Land being annexed and rezoned now is a later chapter. For the next few years, the town's new-construction market works more like a fixed set of choices than an open pipeline.

Why a Sewer Line in Davidson County Sets Supply in Williamson County

Nolensville sits in Williamson County, but Metro Nashville provides sewer service for this part of town. Town staff put it plainly in the 2026 reports. Utilities are available to the properties "other than sewer services," and "the Town remains in discussion with Metro Nashville who is the sewer provider for this area for when availability will return."

The pause began earlier. At the town's annual address on April 29, 2025, Town Manager Victor Lay said Metro Water and Sewer had told the town it was "essentially not allowing any future development approvals until they reach some agreements with TDEC and expand their capacity." According to the Williamson Herald's coverage, he said Metro's two lines in town were at 80% capacity, which is Metro's threshold for allowing more development plans. In the same remarks, Lay said the town had already approved around 2,200 homes that would be built over the next decade, so he did not expect the pause to stop growth in the short term. Those figures date from spring 2025, and no 2026 update to the count has been published. What the 2026 staff reports do confirm is that the pause on sewer availability is still in place.

So the town's supply has two layers. One layer is projects that were approved before the pause, and those are being built and sold. The other is everything since, which can win annexation and rezoning but cannot count on sewer service.

What's Actually for Sale Right Now

Every active community below dates from the earlier layer. Prices are builder-published figures as listed on October 10, 2026.

Community Builder or developer What the builder shows as of October 10, 2026
Fairington Southern Land Company / SLC Homes "Now Selling"; listed inventory from $822,825 to $1,439,900
The Mill at McFarlin Beazer Homes Cottages and Estates; plan prices from $699,990 to $899,990
Willow Ridge John Wieland Homes Starting in the low $1.1 millions; plans of 3,775 to 4,403 sq. ft.; interest list, no quick move-in homes
Annecy Celebration Homes, Ernst Group via AR Homes Celebration advertises "Final Opportunities" from $1 million; AR Homes lists three homesites at $350,000 to $375,000
Sagebrook Toll Brothers Still listed as a future community with a VIP list and no public pricing

The table shows a narrow menu. Annecy is in its last stretch. Celebration's wording is "Final Opportunities," and the three AR Homes lots run from 0.46 to 0.83 acres, with Ernst Group custom homes starting at $1.5 million. When Toll Brothers announced Sagebrook in February 2026, it planned just 26 single-family homes and expected to start sales in fall 2026. The Willow Ridge sales page still points buyers to an interest list.

That leaves the two large communities carrying most of the volume.

Fairington is Southern Land's 373-acre master plan. When construction began on Fairington Club in February 2026, the company described a finished community of more than 700 homes, 160 acres of green space, and a 15,000-square-foot retail and restaurant component at Village Commons. The February release put the Club's opening in 2027, while the current Fairington homepage says December 2026. Housing types range from townhomes to estate homes on half-acre lots, so this single community covers much of the town's new-construction price range.

The Mill at McFarlin broke ground in November 2025, according to WSMV's report. The Williamson Herald reported 444 detached homes, including about 200 rear-loaded lots, 160 lots 80 feet wide, and 80 lots measuring 100 by 150 feet. At groundbreaking, Beazer expected prices of $799,000 to $869,000. As of October 10, 2026, its published plan prices run from $699,990 to $899,990, a wider range at both ends than the original estimate.

Why Rezoned Land Isn't Near-Term Supply

The 2026 planning agendas can make it look like the next wave is already lined up. The Planning Commission unanimously recommended annexing and rezoning the 337-acre Van Slyke Farm on Nolensville Road in May 2026, from MGA-1 to CD-2. Kidd Road's 51-lot concept and Greenbrook East's 21 townhomes on Rocky Fork Road both received favorable staff recommendations.

Each report attaches the same condition, and on Van Slyke Farm staff noted there is no immediate development plan. The Kidd Road concept plan is labeled non-binding. Annexation and rezoning decide what land may become. Without sewer availability, the steps that put a house on a lot cannot be counted on. A buyer who hears about "the big farm that just got approved" is hearing about land use, and a buildable home could still be years away.

This changes the comparison with neighboring towns. When a buyer weighs a Nolensville new build against one elsewhere in Williamson County, both new-construction markets may look active. In Nolensville, the number of active communities is limited until sewer capacity returns.

The Project That Could Reopen the Pipe

Metro Water Services lists a Nolensville Sewer Replacement Project, number 25SC0020, with Garney Construction as contractor. It will replace about five miles of 12- to 24-inch sewer main along Mill Creek with 18- to 42-inch main "to accommodate the growth in the area," and work is scheduled from November 2026 through November 2028.

The timing roughly matches Lay's 2025 remark that Metro thought it could resolve the issue "in about three years." Metro's project page does not say that sewer availability will return when construction finishes. A separate, larger fix for the region, the Mill Creek Trunk Improvements and Equalization Facility, is on hold while Metro reevaluates its options for sewer overflows and projected growth in the Mill Creek sewershed. Its listed timeline shows design from 2027 to 2030 and construction from 2031 to 2037.

The roads are on a slow schedule too. In April 2026 the town announced that TDOT had placed the Nolensville Road widening from Sunset to Burkitt in its 10-year plan, with construction targeted for 2036. The town committed $500,000 to preliminary engineering in 2027 and $10.5 million toward construction. On TDOT's separate project for State Route 11, Phase I north of Mill Creek is expected to finish in July 2027. Supply and roads are each waiting on their own long-term fix.

Questions That Matter More in Nolensville Than Elsewhere

Since the menu is close to fixed for now, the useful questions are about where a given home sits in its community's build-out:

  1. Which phase is this, and how much of the community is still unbuilt? Builders often don't publish lot counts. Fairington's and Willow Ridge's pages don't list them, so ask the sales office directly.
  2. When are the promised amenities due? Fairington Club has two published opening dates, and Beazer refers to future amenities at The Mill at McFarlin.
  3. What is planned next to the lot? Nearby land may be annexed and rezoned but still waiting on sewer, so it could stay undeveloped for a while and then change all at once.
  4. How might resale competition look later? A neighbor reselling in a community that is still building may compete with the builder's own new inventory.

A Few Common Questions

Is there a building moratorium in Nolensville? No formal town moratorium has been found in the record. The limit comes from Metro, which is not issuing sewer availability for new development, according to 2026 town staff reports.

Will the Mill Creek sewer project end the pause in 2028? Metro schedules the work from November 2026 through November 2028, but its project page does not say when availability will return.

Does the court case over impact fees affect new-home buyers? The Williamson Herald reported that Chancery Court ruled the town lacked authority to charge impact fees and ordered fees collected from Home Builders Association of Middle Tennessee members since August 6, 2020, to be refunded. Commissioners voted unanimously to appeal. No outcome of the appeal has been reported, so any effect on builder costs is still unknown.

If you're choosing between Fairington, The Mill at McFarlin, Willow Ridge or a resale in Nolensville, or you own a home here and want to know how a fixed new-construction supply affects your home's value, Mary Brown and Jackie can go through the phase maps, amenity timelines and comparable sales with you. Request your home valuation and we'll start there.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.